ToggleSteam Line Insulation and Ironing Room Energy Efficiency
Since 1971, Malkan Machinery has manufactured industrial ironing machines for the garment and laundry sectors. In a news article published on December 24, 2009, the company introduced R-ENERGY (originally named R-ENERJI), a system developed to reduce energy costs for its customers. At the heart of the system were special steam line insulation techniques that minimize energy losses.
Mustafa Alkan, General Manager at the time, answered questions about the new system and its applications. Alkan, who has carried the effort, name and quality approach of Malkan Machinery since 1971, delivered a clear message: as energy costs rise, competitiveness is protected in the steam line, in the boiler room and at the ironing table.
This article expands that interview with today's technical knowledge.
Steam line insulation is the most visible part of this approach, yet it is not sufficient on its own. Without the right boiler, a line of the right diameter and slope, well-placed machines and a trained maintenance team, steam line insulation cannot deliver the expected efficiency. The sections below take up this chain link by link.
The 2009 Interview: The Aim of the R-ENERGY System

The first question of the interview asked which innovations Malkan Machinery offered its customers and which features set its products apart. Mustafa Alkan began his answer with a problem shared across the sector: energy costs in garment and laundry businesses were rising day by day. This increase directly affected manufacturers' price competitiveness.
According to Alkan, the solution was to cut costs where production consumes the most energy: the steam system. R-ENERGY was developed for this purpose and aimed in particular to minimize energy losses in steam lines. The system used special steam line insulation techniques, while boiler selection and correct steam line installation were carried out by Malkan Machinery engineers.
According to the interview, the system had also begun to be applied in international projects by 2009. Alkan considered the selection of ironing machines and their placement according to the factory layout part of the same chain. He stressed that preventing losses at steam inlets and outlets alone provided businesses with considerable savings.
After installation, businesses received maintenance training and training on correct material use. The aim was to ensure that the savings continued after the installation team had left. Steam line insulation, boiler selection, layout and training were thus offered as a single package.
Sources of Energy Loss in Steam Lines

Steam releases heat from the moment it leaves the boiler. An uninsulated steel pipe loses more energy as its surface area and the temperature difference grow, and the lost heat returns along the line as condensation. Condensed water lowers the quality of the steam reaching the ironing machine and increases the risk of wet spots on the fabric.
The first source of loss is uninsulated straight pipework. The second is irregular surfaces such as valves, flanges, strainers and steam traps; because these parts are removed and refitted during maintenance, many plants leave them exposed. The third is invisible leakage: loose fittings, worn gaskets and steam traps stuck open release live steam directly.
The fourth source comes from design. Excessively long lines, dead legs leading to unused machines and pipes of the wrong diameter consume energy even when no ironing table is working. For this reason, steam line insulation planned without first mapping the losses solves only part of the problem.
Losses also have a quality dimension: for ironing machines, not only the pressure but also the dryness of the steam matters. As steam cools along the line, it begins to carry water droplets, and this wet steam reaches the ironing surface and the fabric as water. The result is longer drying, shine marks and the need to re-iron.
Wetness has two sources: condensation in the line and water carried over from the boiler. The first is largely controlled through steam line insulation and proper drainage, the second through correct boiler selection and operation. A steam separator installed on the main line ahead of critical consumers also removes droplets and discharges them through a steam trap.
Dry steam shortens the warm-up time of the ironing machine and helps keep the ironing surface temperature stable throughout the day. The operator finishes the same garment with fewer repeats, which means both energy and labor efficiency. For this reason, steam line insulation and drainage are as much a quality investment as an energy investment.
Selecting the Insulation Material
The first criterion for material selection is operating temperature. The temperature of saturated steam rises with pressure, so the continuous service temperature of the selected product must stay above the highest temperature in the line. The manufacturer's data sheet is the first document to consult for steam line insulation.
Industrial steam lines commonly use stone wool (mineral wool) pipe sections and mats, as well as calcium silicate and cellular glass. Glass wool is preferred for lower-temperature applications. Rubber-based foams are mostly intended for cooling and low-temperature lines; their temperature limits must be checked before any use on steam.
Moisture is the greatest threat to steam line insulation. Wet insulation conducts heat far more easily and soon loses its function; it can also accelerate corrosion on the outer surface of the pipe. Steam line insulation is therefore protected by an outer cladding such as aluminum or galvanized sheet, with joints overlapped so that water cannot enter.
Mechanical strength also matters. On low lines where forklifts, transport carts and operators pass, steam line insulation is exposed to impact. Crushed insulation loses its thickness; at such points steam line insulation is reinforced with hard cladding or a protective cage.
Valves, Flanges, Hangers and Fittings: The Overlooked Points
The most common mistake in plants is to insulate straight pipes carefully while leaving valves and flanges exposed. A valve body has a much larger surface than straight pipe of the same length and loses heat accordingly. Considering that an ironing department contains dozens of valves, strainers and steam traps, the total loss is far from negligible.
At these points, the solution for steam line insulation is removable insulation jackets. These jackets are fastened with hook-and-loop strips, straps or hooks; the maintenance team removes the jacket to reach the valve and refits it when the job is done. Unlike permanent insulation, the jacket is not torn off and discarded during maintenance.
A jacket works only under two conditions. First, it must fit the part closely and not let air in at the edges. Second, refitting the jacket after maintenance must become a habit; the training step in the R-ENERGY approach targeted exactly this habit.
Hangers and expansion need the same care: a steam line lengthens as it heats up; if this expansion is ignored, both pipe connections and steam line insulation are damaged. Long lines use expansion joints or loops, and hangers are selected to allow the pipe to slide. The insulation cladding is likewise applied with overlaps that accommodate this movement.
Pipe hangers and supports can create thermal bridges. Points where a hanger pierces the insulation and touches the pipe directly appear as hot lines on a thermal camera. When steam line insulation is planned, load-bearing insulation blocks or insulated hanger elements are preferred at hanger locations.
Insulation Thickness, Standards and Occupational Safety
For steam line insulation, thickness is not chosen by eye. As thickness increases, heat loss falls but material and labor costs rise; the point where the two curves balance is called the economic thickness. Pipe diameter, operating temperature, ambient conditions, annual operating hours and energy price are the inputs to this calculation.
An international reference for calculation methods is the EN ISO 12241 standard. The standard covers calculation rules for the thermal insulation of building equipment and industrial installations; heat loss, surface temperature and condensation risk can be assessed with these rules. Documenting the engineering calculation with such a method is recommended when steam line insulation is designed.
The thickness calculation considers not only energy but also occupational safety. Exposed hot surfaces carry a serious burn risk at heights an operator may touch by accident. For this reason, the outer surface temperature of the cladding is also defined as one of the project targets.
Uninsulated steam lines do not only lose energy; they also heat the ironing department. Especially in summer, hot pipes running near the ceiling raise the temperature of a workspace already full of steam and hot surfaces. This increases operator fatigue and places additional load on the ventilation system.
Well-applied steam line insulation provides a more comfortable workspace by reducing the heat released into the room. The risk of accidental contact with hot surfaces also falls, which is particularly important in narrow passages between machines. A comfortable environment also helps maintain ironing quality until the end of the shift.
Boiler Selection and Line Design

The second link Mustafa Alkan emphasized in the interview was boiler selection. The boiler is sized according to the simultaneous steam demand of the ironing department, the operating pressure of the machines and the shift pattern. An oversized boiler operates inefficiently at low load, while an undersized one causes pressure drops and wet steam during peak hours.
In line design, pipe diameter, flow velocity and pressure loss are evaluated together. A narrow pipe lowers pressure and may generate noise; an oversized pipe loses more heat through unnecessary surface area and increases the cost of steam line insulation. The right diameter is the most economical one that delivers sufficient pressure to the farthest ironing table.
The main line is laid with a slight slope in the direction of flow and fitted with drain pockets and steam traps at regular intervals and at every low point. An air vent is fitted at the line end. This arrangement removes condensate quickly and prevents water hammer, one of the most dangerous problems in steam lines.
Pressure Reduction and Distribution Layout
In many plants, steam is generated in the boiler at a pressure suitable for distribution and reduced close to the point where machines need it. This allows smaller-diameter pipe on the main line and therefore less surface heat loss. A pressure reducing station consists of a strainer, a pressure reducing valve, a safety valve and pressure gauges.
Downstream of the pressure reducing valve, the steam temperature drops to the value corresponding to the lower pressure, which reduces surface losses on the machine side. The station itself, however, is full of valve and body surfaces, and steam line insulation should cover it with removable jackets. Otherwise, part of the efficiency gained is lost here.
Another distribution option is to feed machine groups with different pressure needs from separate branches. When different consumers such as ironing tables and presses share the same line, pressure fluctuations can affect one another. Grouping carried out at the planning stage prevents costly changes later.
Ironing Machine Layout and Steam Connections
The third topic emphasized in the interview was the selection of ironing machines and their placement according to the factory layout. When machines are positioned far from the main line and scattered, each needs a long branch line. Every additional meter means additional insulation, additional loss and an additional maintenance point.
In a good layout, ironing tables and machines such as form ironing presses are arranged in orderly groups that follow the production flow, and the main line passes over these groups by the shortest route. Branches are taken from the top of the main line so that condensate is not carried to the machine.
Lines leading to unused machines are isolated with a valve or removed, without leaving a dead leg. Machine inlet and outlet points, as Alkan emphasized, are an important savings area even on their own. The inlet valve, strainer, flexible connection and steam trap assembly are arranged close to the machine, accessible and easy to insulate.
When these small assemblies are installed with care, steam line insulation continues without interruption right up to the machine.
Steam Traps and Condensate Management
A steam trap is an automatic valve that holds back steam while discharging condensate and air. Thermodynamic, float, inverted bucket and thermostatic types suit different load and pressure conditions. If the wrong type is selected, the trap either passes steam or fails to discharge water in time.
A steam trap that fails open releases live steam into the condensate line; this loss often goes unnoticed because everything appears to be working from the outside. A trap that fails closed causes water to accumulate inside the machine, prevents the ironing surface from heating and leaves water stains on the fabric. Both conditions require regular testing.
Discharged condensate is still hot and valuable water. Returning it to the boiler feedwater saves energy as well as water and chemical treatment. Condensate return lines are also insulated as part of steam line insulation; otherwise the recovered heat is lost on the way.
Commissioning, Measurement and Leak Detection
Once installation is complete, the system is handed over with measurements. A thermal camera shows missing or damaged steam line insulation through color differences; exposed valve bodies and crushed sections are easily caught in this scan. Cladding surface temperatures are recorded with a contact thermometer.
The condition of steam traps is checked with ultrasonic listening devices and temperature measurement. Continuous hissing may indicate a trap stuck open, while a cold trap suggests a blockage. Findings are entered on a checklist, and problem parts are numbered.
The first measurement is the reference for all later checks. The same measurements are repeated when steam line insulation is renewed or a new machine is added to the line. In this way, the continuity of the savings is tracked through records rather than estimates.
Prioritizing the Losses
In an existing plant, it is rarely possible to fix everything at once. A loss map is therefore drawn up first: lengths of uninsulated line, the number of exposed valves and flanges, leak points and faulty steam traps are gathered in a single list. The estimated loss and correction cost of each item are written side by side.
Live steam leaks and steam traps stuck open usually come first; they can be fixed at low cost and stop the loss directly. Removable jackets for exposed valves and flanges follow, then uninsulated straight lines. Closing dead legs and removing unnecessary branches are also among the early steps of the plan.
The payback of a steam line insulation investment depends on the plant's operating hours, steam pressure and fuel price, and must be calculated separately for each plant. When the calculation is based on initial measurements, the investment decision rests on data rather than estimates. This also makes budget approval easier.
Maintenance Training and Correct Material Use
The final link of the R-ENERGY approach was training. After installation, the plant's maintenance team was shown how to check the line, which part to test at what frequency and how to read signs of failure. Training on correct material use aimed to prevent repairs made with the wrong gasket, the wrong insulation or unsuitable fittings.
The practical outcome of the training is a set of simple rules. A removed insulation jacket is refitted when the job is done, and wet insulation is replaced rather than dried. An operator who notices a leak reports it to the maintenance team the same day.
These rules seem small, but they determine the life of the steam line insulation investment. Valves left exposed and cladding crushed a few months after installation quietly erode the savings of the first day. A trained team is the most economical way to keep the system in its original condition.
This discipline, based on measurement and records, is also the foundation of the quality approach at Malkan Machinery. The Gold Award the company received within the TSE Quality Awards is one of the corporate indicators of this approach.
Why the 2009 Approach Remains Valid Today

Over the years, ironing machines, control systems and boiler technologies have advanced, but the physics of steam has not changed. A hot pipe still releases heat to its surroundings today, and an open steam trap still passes steam. For this reason, the logic established in 2009 remains the first checklist for new investments.
Today, energy efficiency is not only a matter of cost; it is also a topic raised in customer audits and sustainability reports. Measuring and documenting losses in the steam system makes it easier to answer these questions with concrete data. Steam line insulation is one of the first steps to deliver measurable results.
The product range of Malkan Machinery includes steam boilers as well as ironing machines. This integration allows the entire chain, from the boiler to the ironing table, to be planned with the same engineering perspective. Export experience reaching 95 countries also brings knowledge from plants operating in different climates and energy conditions into this planning.
The Thermo Steam boiler introduced at Garment Tech Istanbul 2025 is one of the current examples of this integration. Field experience is shared with businesses at international events such as the CAITME 2026 exhibition in Tashkent and HOSTECH 2026. The current goals of the company are set out in detail in the Malkan Vision 2025-2026.
Conclusion: Steam Line Insulation Is the First Link in the Chain
Steam line insulation is the most visible way to reduce energy loss in an ironing department. Lasting results, however, come together with the right boiler, a well-designed line, carefully placed machines and a trained maintenance team. The R-ENERGY approach announced by Malkan Machinery in 2009 brought these links together in a single package.
When these five links (boiler selection, line design and insulation, machine layout, condensate management, and measurement and maintenance training) are managed together, efficiency becomes lasting.
Frequently Asked Questions (FAQ)
Where does steam line insulation make the biggest difference?
On uninsulated straight pipes, on irregular surfaces such as valves and flanges, and on machine inlet and outlet assemblies. These points are easily identified with a thermal camera.
Why are valves insulated with removable jackets?
Valves must be accessible during maintenance. Because a removable jacket can be taken off and refitted, the insulation stays in place after maintenance.
Why should wet insulation be replaced?
Wet material conducts heat far more easily and can accelerate corrosion on the pipe surface. Drying rarely restores its original performance.
How is a steam trap failure detected?
It is detected with ultrasonic listening and temperature measurement. Continuous hissing may indicate a steam leak, while a cold body may indicate a blockage.
When does a steam line insulation investment pay back?
Payback depends on operating hours, steam pressure and fuel price. The correct calculation is made separately for each plant using initial measurements.
How is boiler size selected?
It is selected according to the simultaneous steam demand of the ironing department, the operating pressure of the machines and the shift pattern. An oversized boiler operates inefficiently at low load.
Why does an ironing department need dry steam?
Wet steam reaches the fabric as water, prolongs drying and can cause shine marks. Steam line insulation, drainage and a separator help keep the steam dry.
What did the R-ENERGY system cover?
Announced in 2009, the system covered special steam line insulation techniques, boiler selection, correct line installation, machine layout and post-installation maintenance training.
Plan Steam Line Insulation and Energy Efficiency Together
Identify where steam is lost in the ironing department together with Malkan Machinery engineers. From boiler selection to machine layout and from steam line insulation to maintenance training, plan the plant as a whole and draw up a roadmap that improves both the energy bill and ironing quality.
Plan a Technical Consultation →Resources and Detailed Information
- Wikipedia – Thermal insulation – Definition and basic principles of thermal insulation https://en.wikipedia.org/wiki/Thermal_insulation
- Wikipedia – Boiler – Function and operating principles of boilers https://en.wikipedia.org/wiki/Boiler
- Form Ironing Presses – Malkan Machinery form ironing presses and the Southeast expansion https://malkan.com.tr/en/form-ironing-presses-southeast-expansion/
- Garment Tech Istanbul 2025 – The Thermo Steam boiler introduced by Malkan Machinery at the fair https://malkan.com.tr/en/malkan-garment-tech-istanbul-2025-vision/
- CAITME 2026 – Malkan Machinery at the Tashkent exhibition https://malkan.com.tr/en/caitme-2026-exhibition-malkan-machinery-tashkent/
- HOSTECH 2026 – Malkan Machinery at the hotel and laundry exhibition https://malkan.com.tr/en/hostech-2026-exhibition-malkan-machinery/
- Malkan Vision 2025-2026 – Current goals and roadmap of the company https://malkan.com.tr/en/malkan-vision-2025-2026/
- TSE Quality Award – The Gold Award of Malkan Machinery within the TSE Quality Awards https://malkan.com.tr/en/tse-quality-award-malkan-machinery/
- YouTube – KAR1011S Form Press – Short product video on the Malkan Machinery channel https://www.youtube.com/shorts/A9YlIS7MiQs